Quick Reference
| Item | Detail |
|---|---|
| Rule | 16 CFR Part 1263 — Safety Standard for Button Cell or Coin Batteries and Consumer Products Containing Such Batteries |
| Action | Direct final rule |
| Federal Register | 91 FR 74086 (Doc. 2026-23435) |
| Docket | CPSC-2023-0004 |
| Published | November 18, 2026 |
| Effective | February 13, 2027, unless CPSC receives a significant adverse comment by December 18, 2026, in which case the rule will be withdrawn before its effective date |
| Substantive change | Incorporation by reference updated from ANSI/UL 4200A-2023 to ANSI/UL 4200A-2026 |
| Statutory basis | Reese’s Law (15 U.S.C. 2056e); update processed under section 2(f) |
This is not a new regulatory regime. It is a version change: CPSC codified ANSI/UL 4200A-2023 at 16 CFR part 1263 in September 2023 (88 FR 65274, September 21, 2023) under Reese’s Law. UL Standards and Engagement issued the revised ANSI/UL 4200A-2026 and notified CPSC on August 17, 2026. CPSC published a notice of availability and sought comment (91 FR 56604), received 37 comments, and now proposes to move the incorporated reference to the 2026 edition by direct final rule.
Key Dates
| Date | Event | Importer action |
|---|---|---|
| December 18, 2026 | Deadline for significant adverse comments | Watch for a withdrawal notice; if none, prepare for February 13, 2027 |
| February 13, 2027 | Rule effective; ANSI/UL 4200A-2026 incorporated | Covered products entering the US market must comply with the new reference; certificates and test reports must cite it |
| Before February 13, 2027 | Transition window | Inventory SKUs, refresh test reports, align labels, confirm the tested version with the laboratory |
Where the Obligations Sit
| Obligation | Source in the rule | Practical step |
|---|---|---|
| Performance requirements and test methods | 16 CFR part 1263 incorporates ANSI/UL 4200A-2026, including child-resistant enclosure performance and test methods | Confirm with the laboratory which edition each report was tested to; a report to the 2023 edition will not support compliance after the effective date |
| Warning labels | Reese’s Law section 2(a)(1) requires warnings about the ingestion hazard on packaging, on the product and in product literature; part 1263 carries performance, test-method and warning-label requirements covering packaging, accompanying literature and, as practicable, the product itself | Make packaging, manual and product marking consistent; re-verify wording and placement after the version change |
| Certification | CPSA section 14(a) (15 U.S.C. 2063(a)) requires manufacturers, including importers, to certify compliance with all applicable CPSC requirements; non-children’s products use a general certificate of conformity (GCC), children’s products require testing by a CPSC-accepted third-party conformity assessment body and a children’s product certificate (CPC) | Decide first whether the product is a children’s product; the certificate type and testing route follow from that decision |
| Basis of testing | Certification must rest on a test of each product, a reasonable testing program, or, for children’s products, tests of a sufficient number of samples by a CPSC-accepted third-party laboratory | Retain the testing plan, sample batches and laboratory accreditation for customs and marketplace review |
The rule text does not enumerate every technical difference between the 2023 and 2026 editions. Product-level conclusions require a clause-by-clause comparison against ANSI/UL 4200A-2026.
Categories Commonly in Scope
Remote controls, LED candles and small lights, thermometers and timers, hearing aids and listening devices, small electronic toys, calculators, digital scales, and stationery or small accessories powered by button cells. Whether a specific item is covered still depends on its construction and battery-compartment design.
Impact by Counterparty Type
Manufacturers
Battery-compartment design, fastener method and warning-label layout are the three main remediation lines. Tooling changes are the most expensive item, so confirm construction before February 2027.
Marketplaces and third-party sellers
Marketplace review and CPSC eFiling both draw on certificate data. A certificate still citing the 2023 edition will not match the rule after the effective date.
Importers of record
Importers are themselves the certifying party under CPSA section 14(a). Confirm the edition on the supplier’s report before the cargo sails, not after it arrives.
Frequently Asked Questions
1. Is this a new standard or an update?An update to 16 CFR part 1263, principally moving the incorporated reference to ANSI/UL 4200A-2026.
2. Could it fail to take effect?Yes. If CPSC receives a significant adverse comment by December 18, 2026, it will withdraw the direct final rule before the effective date.
3. CPC or GCC?Determined by whether the product is a children’s product. Children’s products require third-party laboratory testing and a CPC; non-children’s products use a GCC.
4. Do existing stocks need rework?The effective date is February 13, 2027, and covered products entering the US market after that date must meet the new reference. Assess inventory by arrival date.
5. Is a packaging-only warning enough?No. Packaging, product literature and, as practicable, the product itself all carry warning obligations.
Action Checklist
- List every SKU containing a button cell or coin battery, with battery model, compartment design and children’s-product status.
- Ask the laboratory which edition each existing report was tested to and flag what must be retested.
- Check warning wording, placement and legibility against ANSI/UL 4200A-2026 across packaging, manual and product.
- Update the CPC or GCC so the cited standard edition matches the rule.
- Set review points at December 18, 2026 (withdrawal check) and February 13, 2027 (full switch).
Related Reading
- Button Battery, Water Beads and Small Parts: CPSC High-Risk Categories
- CPC Children’s Product Certificate Complete Guide
- CPSC eFiling 2026: ACE Will Not Auto-Reject
Contact us for a compliance review — send the SKU list and current test reports and we will map the version gaps, then coordinate testing and space.

Leave a Reply